Few development sites are worth purchasing before planning permission is secured. Equally, waiting until consent is granted leaves the land vulnerable, as the owner could sell it elsewhere while the application is being processed.

A conditional contract fills this gap. Both parties commit at exchange but the obligation to complete only arises once an agreed condition is met.

Below, we explain how these contracts operate under English and Welsh law, how the condition precedent should be defined, and what each side needs from the drafting.

What is a conditional contract?


It is a binding contract for the sale and purchase of land, entered into in the usual way at exchange, under which completion depends on a stated condition precedent being met. Satisfactory planning permission is the most common trigger.

The price is fixed, the completion process is agreed, and the Seller must still provide title and comply with every other obligation. What remains outstanding is the event that converts the agreement into an unconditional one.

How it differs from an ordinary sale contract


Under a conventional contract, completion follows exchange on the agreed date and neither party can withdraw. Conditionality changes only the timing and the trigger, not the binding nature of what has been signed.

Both parties remain bound by section 2 of the Law of Property (Miscellaneous Provisions) Act 1989, which requires any contract for the sale of land to be in writing, to incorporate all agreed terms, and to be signed by or on behalf of each party.

What counts as "satisfactory planning permission"?


Only what the contract defines. There is no statutory definition, so the test is determined by what the parties agree – and clarity at this stage is what distinguishes a functional agreement from a costly dispute. As with any contract, ambiguous conditions invite future arguments about whether the trigger event has occurred at all.

Setting out objective criteria in full is therefore essential. Depending on the scheme, these may include:

  • Minimum unit numbers, floor areas, or developable acreage.

  • A cap on total Section 106 contributions and Community Infrastructure Levy liability.

  • Exclusion of specified onerous conditions, such as restrictive phasing or abnormal highways works.

  • Expiry of the six-week period for judicial review or statutory challenge without proceedings being issued.


Leaving the test to the Buyer's absolute discretion has important consequences. Drafted this way, the contract functions much like an option agreement, as one party alone decides whether to proceed – and a Seller agreeing to such terms should factor this risk into the pricing.

Other conditions precedent


While planning permission is the most common trigger, it’s not the only one. Ground investigation results, satisfactory searches, third-party consents, and confirmation that no town or village green application affects the land are all common requirements. Each needs the same treatment:

  1. a clear test;

  2. a defined timescale;

  3. and an agreed method for resolving disagreement.


When are conditional contracts used?


Development is the usual context. A Buyer who intends to build needs certainty that the land will still be available once permission has been obtained, while a Seller wants commitment rather than an open-ended tie-up.

Situations where the structure works well include:

  • Planning-led purchases: the Buyer applies for consent at its own cost, knowing the site cannot be sold to a competitor in the meantime.

  • Regulatory consents: premises licences, environmental permits, and listed building consent all lend themselves to a defined condition.

  • Infrastructure agreements: a scheme may depend on highways and drainage adoption agreements under sections 38 and 104, so completion can be made conditional on those being in place. Easements and wayleaves for utility connections can be treated the same way.

  • Interdependent purchases: where a developable plot and separate access land must be acquired together, each contract can be made conditional on the other completing.

  • Title and tenure issues: lease extensions, vacant possession, or the removal of a registered restriction can all form the condition.


Residential and mixed-use acquisitions follow similar principles, though development transactions account for most of the conditional contracts we prepare.

How does a conditional contract work?


1. Exchange


Parties exchange contracts incorporating the condition precedent, usually alongside the Standard Commercial Property Conditions (Third Edition, 2018 Revision). A deposit is paid, often smaller than on an unconditional sale, and frequently with a non-refundable element to compensate the Seller for taking the site off the market.

2. Satisfying the condition


The Buyer pursues the relevant application or consent, within whatever timescales the contract imposes. Notice is then served confirming that the condition has been met, and the contract becomes unconditional at that point.

3. Completion


Completion proceeds on the timetable set out in the contract, typically a fixed number of working days after the notice. From here, everything runs as it would on any other property purchase.

4. The longstop date


Where the condition remains unsatisfied by the agreed longstop date, the contract comes to an end. Termination may be automatic or exercisable by one or both parties, and the drafting should say which.

Setting that date realistically matters more than it appears. Planning determination periods, committee cycles, section 106 negotiation, and any appeal all need accommodating, because a longstop date that expires mid-application serves nobody.

What obligations will the Buyer take on?


A Seller receives no comfort from a contract that leaves the Buyer free to do nothing. Positive obligations are therefore standard, and commonly require the Buyer:

  • To submit a draft planning application to the Seller for approval within a specified period after exchange.

  • To use reasonable endeavours to obtain satisfactory permission as soon as reasonably practicable.

  • To appeal a refusal, often where planning counsel advises that prospects of success exceed an agreed threshold.

  • To keep the Seller informed of progress and to supply copies of decisions.

  • Not to implement any permission granted before completion of the purchase.


Endeavours wording requires attention. Reasonable endeavours, all reasonable endeavours, and best endeavours impose materially different burdens, and the distinction has been litigated often enough that it should never be left to chance.

Risks for the Buyer


Abortive cost is the obvious one. Consultants, application fees, surveys, and legal expenditure are all irrecoverable if the condition is never satisfied.

More serious is the risk of being bound to complete on terms that no longer work. Once permission meeting the contractual definition is granted, the Buyer must proceed regardless of how the market or funding have moved in the meantime. That is precisely why the definition of satisfactory consent deserves such care.

What obligations will the Seller take on?


Developers expect reciprocal commitments, since an uncooperative owner can frustrate an application entirely. Typical Seller obligations include:

  • Assisting with the planning application and entering into any section 106 agreement required as a condition of consent.

  • Opposing any town or village green application affecting the land, and challenging registration where necessary.

  • Not altering the character of the property or granting leases, charges, or other interests without consent.


Restrictions of this kind are reasonable while the contract runs, though a Seller should ensure they fall away automatically on termination.

Risks for the Seller


Loss of control is the principal exposure. The land cannot be marketed elsewhere and the Seller is dependent on the Buyer's diligence in pursuing an application over which it has limited influence. With the price fixed at exchange, many Sellers also negotiate an overage payment.

Legal considerations before exchange


Protecting the contract at HM Land Registry


A conditional contract creates an estate contract and it should be protected by a notice against registered title or, for unregistered land, a Class C(iv) land charge. Without registration, a purchaser of the land may take free of the Buyer's interest entirely.

Sellers sometimes resist, since the entry affects their ability to deal with the property. Agreeing in advance how and when the notice will be removed on termination usually resolves the point.

Waiver, variation & dispute resolution


Most conditional contracts permit the Buyer to waive a condition and proceed with completion, which may be commercially sensible where a permission is slightly deficient but the overall scheme remains viable. Whether the Seller holds a similar right is a matter for negotiation.

Disputes over whether a condition has been satisfied should never default to litigation. Expert determination, with a clear timetable and an agreed appointing body, provides a much faster and significantly cheaper resolution.

Speak to our commercial property solicitors


Conditional contracts reward careful drafting and can be detrimental if not handled properly. The same structure can either protect a developer's position or commit them to an unwanted purchase, depending entirely on how the condition and the obligations are worded.

Our commercial property solicitors advise landowners, developers, and investors across London on conditional contracts, option agreements, promotion agreements, overage, and the acquisitions that follow once a scheme is secured.

Get in touch to discuss your site and the most appropriate structure for it.
Our clients
Prev Arrow
Next Arrow